City Commission Reviews Design Development Drawings

Enid City Commision will review the Enid Renaissance vision and approve the design development drawings for the new event center and renovation of Convention Hall by Convergence Design and Flintco Constructive Services, Inc.

The design team requested that the date of April 19, 2011 for the Event Center and Convention Hall renovation Guaranteed Maximum Price (GMP) be revised to April 29, to allow the project GMP to be based on a 100% design development that will be completed on April 8 by Convergence Design. As provided in the contract, Flintco Constructive Services, Inc. will produce a project GMP 20 days after the completion of design development.

GMP project timeline:

  • April 5: 90% Design Development (drawings, budget and schedule)
    presentation to the City Commission for approval
  • April 8: 100% Design Development available to Flintco
    Constructive Services, Inc. to prepare the project GMP
  • April 25: Project GMP provided to the City Commission for review
    and comment by Flintco Constructive Services, Inc.
  • Special City Council meeting for review and approval of GMP
    presentation to be determined